Construction of Plavinas HPP.
16 March 1964
-
Construction site of Plavinas HPP.
1961
-
Laying the first cubic metre of concrete into the foundation of Plavinas HPP structure.
17 October 1961
-
Construction of Plavinas HPP.
12 December 1963
-
Construction of Plavinas HPP.
9 May 1964
-
Mounting of the turbine of Plavinas HPP.
11 June 1965
-
Mounting of the gantry crane.
7 July 1965
-
Closure of the Daugava when starting to increase the level of water in the reservoir of Plavinas HPP. 16 July 1965
-
200 kVA transformatora nogādāšana Pļaviņu HES būvlaukumā.
1965. gada 5. oktobris Delivery of 200 kVA transformer to the construction site of Plavinas HPP.
5 October 1965
-
Plavinas HPP 330 kV substation.
10 November 1965
-
Concreting of the water sluice of Plavinas HPP.
7 February 1966
-
Mounting of hydropower unit No. 1 of Plavinas HPP. 1 December 1966